Drawing Office Practice and Revisions
≈ 34 minDrawing Office Practice and Revisions
Drawings live longer than the projects that created them, so they need managing as documents, not just as pictures.
Drawing numbers. Every sheet carries a unique number, and components reference it. The number, not the title, is how a drawing is found — titles are not unique and get edited.
Revisions. When an issued drawing changes, the change is recorded in a revision table: revision letter or number, a description of what changed, the date and who authorised it. The revision letter also appears next to the changed feature so a reader can find it.
Why the history matters. Parts made to revision A still exist in the field. Someone diagnosing a failure needs to know what revision B changed and when, or they will be comparing a part against a drawing it was never made to.
Issue status. A drawing marked preliminary or for information must not be manufactured from. Only an issued, approved drawing is a manufacturing instruction.
Worked example. A bracket's hole moves 5 mm at revision C. Without a revision table, a workshop with an old print makes it at the old position and nobody can tell which is current.
Core checkpoint: A drawing is a controlled document. Its number identifies it, and its revision history explains it.
Why is a drawing found by its number rather than its title?
What must a revision table record?
Why does the revision history still matter after a change has been made?
What happens if an issued drawing is changed without recording a revision?