The Practical Assessment Task

44 min
0/4 practice checks

The Practical Assessment Task

The PAT is a compulsory CAPS project running across Terms 1–3. It is not an examination drawing: it is a design process with the drawings as its evidence, and it is marked on the process as much as the result.

The phases:

  1. Brief and research (Term 1). State the need in your own words, identify who it is for and the constraints, and research existing solutions. Constraints must be measurable — "must fit a 600 mm shelf" rather than "must be small".
  2. Concepts and development (Term 2). Generate several genuinely different concepts as freehand sketches, evaluate them against your stated constraints, and justify the one you take forward. One concept is not a design process.
  3. Presentation drawings (Term 3). Produce the instrument and CAD drawings — working drawings with correct convention, dimensions and title block.

Evidence matters. Keep the rejected sketches. A marker looking for design process needs to see what you considered and why you set it aside. A portfolio containing only the final answer scores poorly even when that answer is good.

Core checkpoint: The PAT assesses reasoning, not just draughting. Constraints stated early are what let you justify decisions later.

Which of these is a properly stated PAT constraint?

Why should rejected concept sketches be kept in the PAT portfolio?

A learner produces three concepts that differ only in colour and corner rounding. What is the weakness?

In which order do the PAT phases run across the year?